BRO Opens Bridge over Teesta River in North Sikkim

New Delhi: In a relief to the residents of Lachen in North Sikkim, the Border Roads Organisation (BRO) on March 21 opened for traffic 360 feet long bailey suspension bridge over Teesta River in Munshithang near Chungthang town.

The 86 Road Construction Company (RCC) of 758 Border Roads Task Force (BRTF), under Project Swastik, commenced the construction of the bridge in October 2019 and completed it in January 2020.

ads

The approach roads to the bridge have also been constructed. The bridge will give impetus to tourism and facilitate the movement of logistics for the Armed Forces deployed in forward areas.

In June 2019, a steel bridge of 180 feet span at the same location was completely damaged due to a massive cloud burst resulting in severing the lines of communication in North District of Sikkim. The connectivity was kept open by routing the traffic through restricted Army land.

More like this

Strategic Collaboration: Rafael and SpearUAV to Develop and Market Iron Wasp

Tel Aviv: Israeli defence companies continue to develop counter-UAS...

Israel’s Glorious Failure Shocks World in Iran Ceasefire Deal

On February 28, hundreds of American and Israeli fighter...

Airbus and Armenia Sign for Six H145 Helicopters  

Donauwörth, Germany. Airbus Helicopters and the Republic of Armenia...

SMPP Partners with KNDS to Manufacture Advanced Loitering Munitions in India

New Delhi/Eurosatory, Paris: SMPP, one of India’s leading defence...

India Space Congress 2026: Masterplan Revealed for Sovereign Mega-Satellite Constellations

Speaking at the high-energy India Space Congress (ISC) 2026...

A Strategic Turning Point

Numbers, in matters of nuclear strategy, rarely tell the...
Indian Navy Special Edition 2025spot_img