Washington: The Pentagon is withholding about $5 million from manufacturer Lockheed Martin for every F-35 stealth fighter the company delivers equipped with an unfinished upgrade, the F-35 Joint Program Office (JPO) revealed.
The figure is the first official dollar amount disclosed by the Pentagon over the delay of a vital upgrade to the fifth-generation fighter, money that Lockheed cannot collect until the full upgrade is complete, expected sometime next year.
After deliveries of jets were frozen for a full year due to lingering issues with an upgrade known as Technology Refresh 3 (TR-3), the Pentagon resumed accepting F-35s outfitted with the enhancement in July. However, officials said then that the government would still withhold payments for upgraded planes since TR-3 is not finished — TR-3 jets delivered for now are reserved for training, and a subsequent software patch expected to enable full combat capability is anticipated next year — though the exact figure for the withholdings was not clear.
According to a JPO spokesperson, that total is roughly $5 million per tail, which “is being withheld and will be released as combat capability is delivered.” The Pentagon has been tight-lipped about how many aircraft have been sequestered by the delivery freeze and did not say how many jets the withholdings extend to.
Lockheed has said the delivery freeze has not affected F-35 production, with the aerospace giant maintaining a rate of 156 jets per year. The company has said in previous financial disclosures that it expects to deliver “between 75 and 110 aircraft in the second half of 2024, primarily in the TR-3 configuration.” (Jets produced in the TR-2 configuration were unaffected by the delivery halt.)
As part of the announcement, the JPO stated that the Pentagon and Lockheed “have reached an agreement for the acceptance and delivery of Technology Refresh 3 (TR-3) enabled aircraft with robust combat training capability,” improving upon an “initial training capability” available when deliveries resumed in July. The JPO could not provide an explanation for the difference in capabilities by press time.
The TR-3 upgrade essentially provides the hardware and software necessary to support a new suite of capabilities known as Block 4. Originally expected in April 2023, the TR-3 effort is about $1 billion over budget, and its troubles have forced Lockheed to forfeit about $60 million in fees associated with the effort.
Once the TR-3 upgrade is finished, withheld dollars will be released, though the process of disbursing those funds was not immediately clear. During a meeting on the sidelines of a ceremony unveiling Poland’s first F-35, the president of Lockheed’s aeronautics division, Greg Ulmer, said that the TR-3 software needed to enable full combat capability remains on track to deliver in 2025.
Raksha Anirveda's editorial desk team brings in the collective experience of creative professionals - a fine mix of senior copy editors, writers, proofreaders and designers. Working as a team, they continuously create, manage, and curate content to sustain the magazine's profile and reputation in line with market trends and achieve magazine's goal.